Construction Delays and Project Cost Overrun: A Case of Regional Cybercrime Center in Gasabo District, Rwanda

Authors

  • Franklin S. Amanya Mount Kenya University, Kigali, Rwanda
  • Gitahi Njenga Mount Kenya University, Kigali, Rwanda

DOI:

https://doi.org/10.53819/81018102t2049

Abstract

The aim of the survey was to understand the relationship between construction delays and cost overrun in Rwanda more specifically in the Regional Cybercrime Center. More specifically, the research addressed the specific objectives of the effect of inexcusable delays, effect of non-compensable delays and examined the effect of compensable delays on the cost overrun of construction of Regional Cybercrime Center. This survey was anchored on the Stakeholder theory and Results Based Management theory. A combination of descriptive and correlation design was used in this study. A population of 45 including procurement officers, logistic officers, budgeting officers, project managers, site engineers, project planners, interior designers, architectures, it managers, it technicians, supervisors and communication technicians in charge of activities regarding construction and other related activities of Regional Cybercrime Center were used.  This study adopted a consensus approach and encompassed the whole population as sample size. Questionnaires were distributed and used in collection of data. The questionnaires were tested for validity and reliability and a Cronbach’s Alpha of over 0.70 was recorded. Information analysis encompassed the adoption of descriptive statistics by use of standard deviation and mean while inferential statistics were done using correlation and regression and the findings presented using tables and figures. The findings showed Pearson correlation of 0.773 between inexcusable delays and cost overrun while adjusted R-square of 0.588 showed moderating effect and also analysis of variance found to be significant at less than 0.005. For the correlation coefficient of 0.657 between non-compensable delays and cost overrun while adjusted R-square of 0.418 showed weak effect and also analysis of variance found to be significant. For the correlation coefficient of 0.799 between compensable delays and cost overrun though adjusted R-square of 0.630 showed moderating effect and also analysis of variance found to be significant. From outcomes, the objectives were achieved and the entire null hypotheses were rejected. For project owners to achieve timely completion of construction projects without having to incur extra costs which lead to project cost overruns, financial resources/project budget necessary to execute the project must be fully committed and set aside to avoid incongruities caused by delay in payments.

Keywords: Construction delays, cost overrun, regional cybercrime center, Rwanda

Author Biographies

Franklin S. Amanya, Mount Kenya University, Kigali, Rwanda

School of Business and Economics, Master of Business Administration (MBA), Project Management, Mount Kenya University, Kigali, Rwanda

Gitahi Njenga, Mount Kenya University, Kigali, Rwanda

Mount Kenya University, Kigali, Rwanda

References

Abderisak, A. & Goran, L. (2015). Implications of Cost Overruns and Time Delays on Major Public Construction Projects. Proceedings of the 19th International Symposium on Advancement of Construction Management and Real Estate, DOI: 10.1007/978-3-662-46994-1_61

Amandin, M.M. & Kule J.W. (2016). Project Delays on Cost Overrun Risks: A Study of Gasabo District Construction Projects Kigali, Rwanda. ABC Journal of Advanced Research, 5(1), 21–34. https://doi.org/10.18034/abcjar.v5i1.55

Bubshait, A.A. and Al-Juwait, Y.A. (2002). Factors contributing to construction costs in Saudi Arabia. Journal of Cost Engineering, 44(5): 30-34

Chandu, A.P., Marawar, D, S., Bhalerao, V.N. (2016). A methodology for ranking of causes of delay for residential Projects. International Research Journal of Engineering and Technology, 3(6), 224–231.

Enas, F. T. & Pandey, R. K. (2013). Study of delay in project planning and design stages of civil engineering projects. International Journal of Engineering and Advanced Technology, 2(3), 456-461

Fugar F.D.K., & Agyakwah, A.B. (2010). Delays in Building Construction Projects in Ghana. Australian Journal Construction Economy, 10 (1): 128-141. https://doi.org/10.5130/ajceb.v10i1/2.1592

Gasasira I, Peter M, & Eugene N. (2016). The causative factor leading to cost overrun in dam construction project in Rwanda: Case study Kinoni one dam construction project. European Journal of Business and Social Sciences. 4(11), 142-68.

Gündüz, M., Nielsen, Y., & Özdemir, M. (2013). Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey. Journal of Management in Engineering, 29(2), 133-139. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000129

Henry A., Ruth, A., & Dan, T. (2013). Investigation into the Causes of Delays and Cost Overruns in Uganda's Public Sector Construction Projects. Journal of Construction in Developing Countries, 18(2), 33–47.

Kaliba, C., Muya, M., & Mumba, K. (2009). Cost escalation and schedule delays in road construction projects in Zambia. International Journal of Project Management, 27(5), 522-531. https://doi.org/10.1016/j.ijproman.2008.07.003

Kasimu, M. A., & Abubakar, D. I. (2012). Causes of delay in Nigeria construction industry. Interdisciplinary Journal of Contemporary Research in Business, 4(2). 785-794.

Kwatsima, S. A. (2015). An investigation into the causes of delay in large construction projects in Kenya. Unpublished Mater thesis at Jomo Kenyatta University of agriculture and technology, Nairobi, Kenya. Retrieved on March 2, 2022 at http://hdl.handle.net/123456789/2424

Le-Hoai, L., Lee, Y.D., Lee, J.Y. (2008) Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE Journal of Civil Engineering, 12(3), 367–377. https://doi.org/10.1007/s12205-008-0367-7

Ndundo F. N., Mbabazi M, Jaya S., & Ephantus N. W. (2016). Institutional factors influencing timely completion of road project in Rwanda: Case of Government Externally Financed Projects. European Journal of Business and Social Sciences, 5(01): 146-59.

Nuhu B., Ibrahim A., Khalid A. & Saud A. (2017). A Systematic Method to Analyze Force Majeure in Construction Claims. MDPI Journals 7(4):115. DOI: 10.3390/buildings7040115

Remon, F. A. (2013). Ranking of delay factors in construction projects after Egyptian revolution. Alexandria Engineering Journal, 52(3):387–406. https://doi.org/10.1016/j.aej.2013.03.002

Saleh A. T. & Abdelnaser, O. (2009). Causes of delay in construction industry in Libya. The International Conference on Administration and Business. Bucharest, Romania

Sambasivan M. & Soon Y. W. (2007). Causes and Effects of delays in Malaysian construction industry. International Journal of Project Management. 25(5): 517-526. https://doi.org/10.1016/j.ijproman.2006.11.007

Samson, Y. (2016). Investigation into road construction Project delays case of KCC and Agatare access roads. Unpublished master thesis at University of Rwanda, College of Science and Technology. Kigali, Rwanda

Singh, R. (2009). Delays and Cost Overruns in Infrastructure Projects: An Inquiry into Extents, Causes and Remedies. Unpublished research at Delhi School of Economics. Delhi, India.

Sweis, G., Sweis, R., Hammad, A.A & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International Journal of Project Management, 26 (8), 665–674.https://doi.org/10.1016/j.ijproman.2007.09.009

Towhid P. & Amiruddin I. (2012). Causes and Effects of delay in Iranian Construction projects. IACSIT International Journal of Engineering and Technology, 4(5), 598-604. https://doi.org/10.7763/IJET.2012.V4.441

Downloads

Published

2022-03-07

How to Cite

Amanya, F. S., & Njenga, G. (2022). Construction Delays and Project Cost Overrun: A Case of Regional Cybercrime Center in Gasabo District, Rwanda. Journal of Entrepreneurship & Project Management, 6(1), 34–52. https://doi.org/10.53819/81018102t2049

Issue

Section

Articles

Most read articles by the same author(s)

1 2 > >>