Risk Management Methods and Performance of Construction Projects; A Case of Rwanda Education Board School Construction Project in Selected Districts

Authors

  • Mr. NIZEYUMUREMYI Narcisse Mount Kenya University, Rwanda
  • Dr. Eugenia Nkechi Irechukwu Mount Kenya University, Rwanda

DOI:

https://doi.org/10.53819/81018102t5290

Abstract

The purpose of the study was to assess the effect of risk management methods on the performance of construction projects, with a specific case study of Rwanda Education Board (REB) School Construction projects in selected districts. Construction projects are still facing the problems generated by little knowledge on methods to be applied while managing different types of risks. Those methods include namely, risk avoidance, risk control, risk retention and risk transfer. In order to explore those various types of risks, the study focused on four objectives: to examine the effect of risk avoidance, risk controls, risk retention and risk transfer on REB School construction project in selected Districts. The study focused on Rwanda Education Board construction projects, with a target population of 122. The researcher employed a descriptive research design and used a census technique to purposively select the entire target population of 122 as the study sample. Questionnaires were utilized as the data collection instrument and were distributed to the aforementioned respondents. The collected data was then analyzed using SPSS to calculate the mean, standard deviation, correlation, and conduct multiple regression analysis. The study found that risk avoidance, risk control, risk retention and risk transfer affect construction project. The results further showed a correlation coefficient (r) of 0.853 meaning that two variables were positively, strongly and perfectly correlated. The study concludes that risk management methods significantly influence project performance in terms of time, quality, and budget. Collaboration and information sharing between clients and contractors play a crucial role in project success, with the involvement of education officers and headmasters being essential for support. The research confirms a strong and positive correlation between risk management methods and project performance, as indicated by a Pearson Correlation Coefficient (r) above 0.8. The study recommends that all stakeholders should work closely hands in hands to ensure that risks are minimized or mitigated at the highest attainable rate. Again, all parties involved in the project should make regular sites supervision to check if the contractor is using resources allocated to him/her rationally to avoid excessive cost. Furthermore, all stakeholders should ensure that the construction work is carried out in compliance with the scheduled time and that the material used is genuine. And finally, while selecting the sub-contractor, in case of risk transfer, the client and the contractor have to consult each other in order to hire the consultant with the highest desirable competence. The study recommends that construction projects, particularly those managed by the Rwanda Education Board (REB) in selected districts, prioritize and implement comprehensive risk management strategies

Keywords: Risk Management Methods, Construction Projects, Rwanda Education Board School Construction, District.

 

Author Biographies

Mr. NIZEYUMUREMYI Narcisse , Mount Kenya University, Rwanda

Department, Mount Kenya University, Rwanda

Dr. Eugenia Nkechi Irechukwu, Mount Kenya University, Rwanda

Department, Mount Kenya University, Rwanda

References

Ahmed, R., Mohamad, N. A. B., & Ahmad, M. S. (2016). Effect of multidimensional top management support on project succes (Vol. 50). an empirical investigation. Quality & Quantity. https://doi.org/10.1007/s11135-014-0142-4

Allen K. (2015). Impact of risk management on project cost: An industry comparison (Vol. 6). Journal of Information Technology & Economic Development.

Babie, E and Mouton, J. (2008). The Practice Social Research. Wadsworth, California.

Bernoulli, D. (2004). Exposition of a new theory on the measurement of risk (Vol. 22 ). Econometrica. https://doi.org/10.2307/1909829

Caniëls, M. C., & Bakens, R. J. (2012). The effects of Project Management Information Systems on decision making in a multi project environment (Vol. 30). International journal of project management. https://doi.org/10.1016/j.ijproman.2011.05.005

Ceric, A. (2003). A framework for process-driven risk management in construction a framework for process-driven risk management in construction projects. Salford, UK: Univesity of Salford.

Chapman, C. B., & Cooper, D. F. (1983). Risk analysis: testing some prejudices. European (Vol. 14). Journal of Operational Research.

Chapman, C., & Ward, S. (2007). Project risk management. (2, Ed.) Process, techniques and insights, Chichester: John Wiley. https://doi.org/10.1016/0377-2217(83)90260-6

Christopher L. Culp. ( 2011). The risk Management Process. Business strategy and Tactics .

Creswell, J. W. (2014). A concise introduction to mixed methods research. SAGE publications.

Crotty J. M. (2008). Research Design: Qualitative, Quantitative, and Mixed Methods Approaches.

Crowell, M. W. (2013). Estimating the United States population at risk from coastal flood-related hazards. In Coastal Hazards. Springer, Dordrecht. https://doi.org/10.1007/978-94-007-5234-4_6

Dean A. Baker. (2015). Benefits and Challenges of Implementing Agile Development in Modular Shipbuilding (Vol. 13). Naval Engineers Journal.

Ellis D.C. (2010). The conscious project leader: How to create a culture of success for your projects, your people and yourself.

Few, R., Scott, Z., Wooster, K., Avila, M. F., & Tarazona, M. (2016). Strengthening capacities for disaster risk management II: lessons for effective support (Vol. 20). International Journal of Disaster Risk Reduction. https://doi.org/10.1016/j.ijdrr.2016.02.005

Fisk, E.R. (2003). Construction Project Administration. 7th Edition. Prentice Hall. New Jersey, USA.

Kerzner, H. (2009). Project management: A system approach to planning, scheduling, and controlling (10th ed.). New Jersy: John Wiley and Son.

Kimball, R. (2010 ). Failure in Risk Managemen. : New England Economic Review.

Milkus, S. and O.R. Sostak. (2008). Modeling the process for defense of third party rights infringed while implementing construction investment projects Tchnol. Econ. Dev.Economy. https://doi.org/10.3846/1392-8619.2008.14.208-223

Moons, K. G., Kengne, A. P., Grobbee, D. E., Royston, P., Vergouwe, Y., Altman, D. G., & Woodward, M. (2012). Risk prediction models: II. External validation, model updating, and impact assessment. Heart (Vol. 98). https://doi.org/10.1136/heartjnl-2011-301247

Morris, P. (2013). Reconstructing project management reprised: A knowledge perspective. Project (Vol. 44). Management Journal. https://doi.org/10.1002/pmj.21382

Neumann, J., & Morgenstern,O. (1953). Theory of Games and Economic Behaviour (3 ed.). .: Princeton, NJ: Princeton University Press.

Newitt J.S. (2014). Construction Scheduling. Principles and Practices.

Roberts, D. (2013). Risk management of electrical hazards: Bridging the gap in understanding hazard versus risk (Vol. 19). IEEE Industry Applications Magazine. https://doi.org/10.1109/MIAS.2012.2215655

Russell D.and Preston J. (2012 ). Project Management from simple to complex .Unpublished Doctoral dissertation. California School of Professional Psychology.

Sifumba, C. M., Mothibi, K. B., Ezeonwuka, A., Qeke, S., & Matsoso, M. L. (2017). The risk management practices in the manufacturing SMEs in Cape Town. Problems and Perspectives in Management (Vol. 15 ). https://doi.org/10.21511/ppm.15(2-2).2017.08

Tinnirello, P. C. (2012). The Project Management Office: A Strategy for Improvement and Success. In New Directions in Project Management . Auerbach Publications.

Tversky, A. (1967). Additivity, utility and subjective probability (Vol. 4). Journal of Mathematical Psychology.

Tversky, A. &. (1975). Judgment under uncertainty: Heuristic and Biases. Science (Vol. 185). https://doi.org/10.2307/1914185

Tversky, A., &Kahneman, D. (1975). Prospect Theory: An analysis of Decision under risk. Econometria (Vol. 47). https://doi.org/10.1016/0022-2496(67)90049-1

Weston, H., Conklin, T., & Drobnis, K. (2018). Assessing and re-setting culture in enterprise risk management. Assurances etgestion des risques/Insurance and Risk Management (Vol. 85). https://doi.org/10.7202/1051319ar

Woodhill J. (Building Construction: Project Management, Construction Administration, Drawings, Specs, Detailing Tips, Schedules, Checklists and Others Don’t Tell You). 2010.

Wysocki, R. K. (2011). Effective project management: traditional, agile, extreme. John Wiley & Sons.

Yembi Renault, B. &. (2018). Identifying factors of risk management for the construction industry. In Creative Construction Conference. Budapest. University of Technology and Economics. https://doi.org/10.3311/CCC2018-070

Downloads

Published

2023-11-17

How to Cite

NIZEYUMUREMYI , N., & Irechukwu, E. N. (2023). Risk Management Methods and Performance of Construction Projects; A Case of Rwanda Education Board School Construction Project in Selected Districts. Journal of Entrepreneurship & Project Management, 7(15), 67–95. https://doi.org/10.53819/81018102t5290