Project Communication Practices and Performance of Construction Project: A Case of Sonatubes-Gahanga-Akagera Bridge Road Project

Authors

  • Ms. Gisele Kamariza Mount Kenya University, Kigali, Rwanda
  • Dr. Eugenia Nkechi Irechukwu Mount Kenya University, Kigali, Rwanda

DOI:

https://doi.org/10.53819/81018102t2184

Abstract

This survey of project communication practices and performance of Sonatubes-Gahanga-Akagera Bridge Road Project. The specific objectives are to evaluate the effects of project board in achieving the performance of  Sonatubes-Gahanga-Akagera Bridge Road Project, to assess how Daily stand up meeting affect the performance of  Sonatubes-Gahanga-Akagera Bridge Road Project, to find out how weekly status report provides the useful information on the performance of Sonatubes-Gahanga-Akagera Bridge Road Project, to ascertain  how a document repository play an important role on the performance of Sonatubes-Gahanga-Akagera Bridge Road Project. Both qualitative and quantitative methods were used in this study's descriptive design. A descriptive survey was conducted in an effort to record the present state of affairs to provide a description of them. There were a total of 140 people included in the study, 60 from the Rwanda Transport Development Agency (RTDA) serving as Client and 80 from the China Road and Bridge Corporation (CRBC) serving as Contractor, all of whom were expected to provide information data relevant to the study's aims. According to the streamlined Slovene methodology, the sample size is 103, and all responders had an equal chance of being included in the sample. The researcher mostly communicated with participants through questionnaire, which included the quantitative questions. The investigator was able to get first-hand knowledge from respondents by asking them qualitative inquiries tailored to the study goals; this method was also useful for gathering data directly relevant to the aims. Other types of statistical analysis were necessary once the obtained data had been processed and put in some sort of tables. Both qualitative and quantitative methods of analysis were used in the conduct of this study, with the latter using SPSS 16.0 for descriptive statistical analysis that included the calculation of means, frequencies, percentages, and standard deviations. According to the data, the Sonatubes-Gahanga-Akagera Bridge Road Project has a high and important mean on the project board for attaining performance at 1.7249. The Sonatubes-Gahanga-Akagera Bridge Road Project benefits from a high mean daily stand-up meeting attendance of 1.6893, which should be maintained. The Sonatubes-Gahanga-Akagera Bridge Road Project had an excellent mean score of 1.6925 on its weekly status report, which gives vital details on the project's progress. The impact of the Sonatubes-Gahanga-Akagera Bridge Road Project on average is modest (1.7702), hence there is room for significant improvement. For the same project's near future, the Rwandan government and Kicukiro district should prioritize the plan's execution via frequent monitoring, inspection, and environmental audit.

Keywords: Communication Practices, Project Performance, Sonatubes-Gahanga-Akagera Bridge Road, Rwanda

Author Biographies

Ms. Gisele Kamariza, Mount Kenya University, Kigali, Rwanda

School of Business and Economics, Mount Kenya University, Kigali, Rwanda

Dr. Eugenia Nkechi Irechukwu, Mount Kenya University, Kigali, Rwanda

Mount Kenya University, Kigali, Rwanda

References

Abudi, G. (2013). Managing communications effectively and efficiently without taking time Away from Managing the Project. New orleans, Louisianna: originally published as a part of 2013 PMI Global Congress Proceedings.

Aggarwal, Y. (2008). Statistic of education. (2nd Ed.) Delhi, Sterling. Ahimbisiwe, A &. (2012). Project Communication, Individual Commitment, Social Networks and Perceived Project Performance. . Affrican business.

AsokoInsight. (1970). Rwandan Family- Owned Construction Companies, Market Insight: Industry.

Brookins, M. (2020). Reasons for Poor Communication in the Workplace. small business.

Bryde, D.J. (2018). Modelling project management performance. International journal of Quality & Reliability.

Campioni, P. (2012). Rwanda Fast Forward, the Many Perspectives that Make Rwanda a Unique Country. Britain: Great Britain, published by PALGRAVE MACMILAN.

Chen, Y. (2008). The Mechanisms of Information communication on Construction Sites, Forum Journal.

Dexter, L. (1970). Elite specialized interviewing. . Evaston, IL, Northern western University.

Fred, D. (2008). Communication theory, Epistemology and Information, philosophy of information.

Goetsh, D. L. (2016). Quality Management for Organizational Excellence, Introduction to total quality. (8th ed.). Pearson.

Goldratt, E. M. (1984). What is this thing called the theory of constraints? North river press, croton on Hudson, NY.

Hamid A. Botiti D. and Mohandes S. (2015). Managing the Delayed Completion on Construction project,. Journal of advanced research in business and management studies.

Imoh, G. (2013). Application of development communication in Africa’s Rural Development Need for a Paradigm Shift. Global Journal of Arts Humanities and Social Sciences, Vol.1, No 4, page, 16.

John. L. (2020). The Critical Role of Communication in Project Management.

Jones, N. (2018). Program theory of change. In SAGE encyclopedia of education Research, measurement, and Evaluation.

Kothari, C. (2004). Research methodology and Techniques (2nd revised Ed.) India, New Age Publishers.

Kalleberg, A. I. (2013). Comparing organizational sampling frames. Administrative science Quarterly.

Kanbanchi. (2021). Importance of using project boards.

Leong, T. K. (2014). Using project performance to measure effectiveness of quality management system maintenance and practices.

Line, R. (2009). Project communication in an internal strategic perspective, corporate communication. An international journal; Vol.14, No.3. Pp.345-357.

Littlehn, S. (1983). Theories of human communication. 2nd ed. Belmont, C.A, Wadsworth.

Misic, S. (2015). Critical drivers of megaproject success and failure.

Nnamseh, M. (2009). The Role of Communication in Business Success. Nigeria Journal of Management Research, Nostrand Reinhold, vol 10, no.1, pp. 70-85.

Noreen, R. G.E. (2011). Managerial Accounting, 14th edition. New York.

Nunnally, J. (1978). Psychometric Theory. McGraw, Hill book Company pp, 86-113. Planning project communication: how it works? (2015). Sweden:.

Prabuddha E. J. (1995). The discrete time cost tradeoff revisited.

Raina R. (2016). Exploring Cultural influence on managerial communication Relationship to job satisfaction, organizational commitment, and the employees’ propensity. International Journal of Business Communication. Business.

Rajkumar, S. (2010). Art of communication in project management. Paper presented at PMI Research: Defining the future of project management, Washington, DC. Newtown square

Rogers, P. (2014). Theory of change. Methodological briefs impact evaluation No. 2 UNICEF.

Saldaňa, J. (2016). The coding manual for qualitative researchers. Los Angeles, Sage.

Silva, M. E. (2014). Performance measurement in project management.

Surbhi., S. (2017). Difference between classification and tabulation, key difference.

Scott, B. (2020). Importance of project schedule and cost control in project management,. Canada.

Scudder, S. F. (1980). Environmental communication. https://digplanet. com/wiki/ environmental communication.

Ssempebwa, R. K. (2013). Project schedule management, Atlanta international University.

Trietsch, D. (2005). Why a critical path by any other name would smell less sweet? Toward a holistic approach to PERT/CPM project management.

Tripathi, P. (2009). Communication Management a Global Perspective. New Delhi: Global India Publications PVT Ltd.

Weber, J. L. (2020). How to make a construction schedule. Project manager.

Weiss, C. H. (1995). Nothing as good theory. Exploring the Theory based evaluation for comprehensive community initiative for children and families.

Downloads

Published

2023-08-08

How to Cite

Kamariza, G., & Irechukwu, E. N. (2023). Project Communication Practices and Performance of Construction Project: A Case of Sonatubes-Gahanga-Akagera Bridge Road Project. Journal of Entrepreneurship & Project Management, 7(8), 94–113. https://doi.org/10.53819/81018102t2184